Metro fund crisis: BMRCL diverted Rs 9,307 crore meant for other phases to cover rising costs as Centre delays approval for the project. Bengaluru: Amid the tug-of-war between Karnataka and the Centre over financing Namma Metro, the BMRCL had to divert Rs 9,307.19 crore meant for other projects (Phases 2A/2B/3) to fund Phase 2, which has seen its cost increase by Rs 9,729.9 crore..